A Migration Job times out after exactly 30 minutes when run manually/interactively in Apps10 IEE, but runs successfully to completion when the same job is run as a Scheduled Background Job instead — is this a new limitation introduced in Apps10?

Answer

This is the standard 30-minute timeout that applies to any interactive/online (foreground) process in IEE generally, not something specific to Migration Jobs or new to Apps10 specifically — any process run manually/interactively that takes longer than 30 minutes will hit this same timeout. Scheduled/Background Jobs have no such time limit and run until completion (or until they hit an actual error), regardless of how long they take. For any migration job (or other process) likely to run longer than 30 minutes, running it as a Scheduled Background Job rather than executing it manually is the recommended approach.