Can a project baseline be created at the sub-project or activity level, not just the whole project?

Answer

Baseline creation is generally only available at the project level, even on recent generations — you can still view baselined cost/hours rolled up or broken down at a lower level once the project-level baseline exists, but the baseline itself isn't something you create separately per sub-project or activity.